Summit Migration Timeline and Responsibilities
First release (mid August)
- Group discovery view with availability service available
- VDX in place with availability service and circulation gateway
- Authentication done via VDX (interim authentication step)
- All Alliance libraries’ holdings available and kept up-to-date in WorldCat (decided not critical for day one—but desirable)
OCLC responsibilities for first release
- Work with Alliance libraries to batch load all records to OCLC—work has begun on this
- Implementation team to send to Alliance implementation questionnaire (first week of June)—answers from this will determine how OCLC implements the discovery view and the delivery (VDX) portions of Navigator
- On-site train the trainer sessions for Navigator/provide documentation for Navigator
- Provide marketing and PR collateral
Alliance responsibilities for first release
- Return implementation questionnaire by OCLC requested deadline(s)
- Work with OCLC batchload staff to load all records and keep them current
- Work with OCLC as needed on the availability service and circulation gateway (work already underway)
December release
- Authentication in place via EZProxy in the group discovery view
- Integration of ILLiad into Navigator
- Integrate Open URL resolver(s) into Navigator
- All Alliance holdings must be up-to-date in WorldCat by this date
Summer 2009
- Tight integration of IFM into Navigator product
- Other things that will come up
|