Summit Migration Working Group: INN-Reach operations and shutdown
This working group is a sub-group of the Implementation Team.
Chair: Nancy Nathanson
Members
| Mark Kibbey, UW (from Implementation Team) |
(206) 543-9718
|
mkibbey@u.washington.edu
|
| Caroline Mann, UP (from Implementation Team) |
(503) 943-7420 |
mann@up.edu |
| Laura Willey, UO |
(541) 346-1915 |
lwilley@uoregon.edu
|
| Lori Pagel, WOU |
(503) 838-8881
|
pagell@wou.edu
|
| Amy Waite, Clark |
(360) 992-2152
|
awaite@clark.edu |
| Raymond Bailey, LCC |
(541) 463-5356 |
baileyr@lanecc.edu |
Meetings: July 17, following Summit Day (approximately 4:15 pm). October 2, Chemeketa CC.
Shutdown plan
Timetable, overview of steps, and specific instructions
Adopting Visiting Patrons
First draft (historical)
Preliminary background information
Example list of shutdown activities
Detailed list and schedule, Cascade shutdown for merger with Orbis (summer 2003)
|