From the Steering Team minutes
Feb. 6, 2004:
We think that the complicated part (doing the
problem-solving between involved libraries) should happen during the summer
when it may be less busy, so we liked the near-ending date to be in early
August. We also liked not stretching this recon project out so very long, so we
thought we might start one month later, following the schedule set by the
former Cascade libraries. We knew, however, that one of the reasons for the
dragged out process experienced by the former Orbis libraries was due to some
libraries not sending their lists to Alliance staff. We pondered how to entice
and excite all libraries to honor their commitment so others can get on with
their work, and other than promising some valuable prize which nobody can
afford, decided to rely on the integrity and good faith of each participating
library.
<snip>
Shirien
will look at former Cascade AAR time schedule and at the former Orbis AAR time
schedule and will combine the two, with the goal of shortening the overall
time. She will submit that to the Steering Team for their approval.
|
Task/who does it |
Cascade |
Orbis |
Recommended |
Notes |
|
Annual Account
Reconciliation (AAR) year: |
April 1 |
March 1 |
April 1 |
|
|
1.
Announce beginning of AAR process by email. |
May 13 |
May 1 |
May 15 |
Alliance staff send email
to sites announcing the beginning of AAR, and asking for lists of items not
returned during the AAR year to be sent to Alliance staff. |
|
2.
Members send lists to Alliance |
June 28 |
June 1 |
June 1 |
Members send their lists to
Alliance staff by date below, in format indicated by Alliance staff. (Correct
format allows speedier consolidation of data and easier creation of the
master list.) |
|
3.
Consolidated list posted on Web |
July 5 |
June 15 |
June 15 |
Alliance staff post the
consolidated list (sorted by call number, to facilitate searching in all
libraries) on the web no later than … |
|
4.
Search for missing items |
July 19 |
June 30 |
June 30 |
Local libraries search own
stacks for all missing items no later than this date, and report items found
on shelf to Alliance staff. |
|
5.
Master list updated |
July 26 |
June 30 |
July 15 |
Alliance staff update the
list as items are reported found, and finish no later than … |
|
6.
New lists posted to Web |
Aug 9 |
|
not needed |
Alliance staff post new
lists sorted by call number, and by owning and borrowing site. (This is not
needed because in the step above, Alliance staff have crossed off the items
which were found. The titles
which have not been crossed off become the basis for each site to solve
problems between themselves and each other institution.) |
|
7.
Problem-solving between libraries |
Aug 9 |
July 7 |
Aug 1 |
Individual libraries solve
problems between themselves and agree that what the Alliance web page says
matches each of their records, and notifies Alliance staff of this agreement
no later than: |
|
8.
Master listed updated (final) |
Aug 9 |
July 15 |
Aug 10 |
Alliance staff make the
adjustments to the Alliance web list as libraries report items resolved
(returned, found, etc.) and finish the final updates no later than |
|
9.
Prepare list of losses, and net difference. |
Aug. 9 |
|
|
Alliance staff prepares a
list, including net difference, for each member. For Orbis, after the initial start-up members did this on
their own as part of the problem-solving task. Need to decide if we want to
ask Alliance staff whether they can do this, or if we prefer to do it on our
own |
|
10.
Clear the transactions |
Aug 9 |
August 15 |
Aug 10 and onward. |
Sites do patron and item
record work. (Borrowing (patron's) site checks in the lost item from the
patron record and then stops a credit for the replacement cost from
occurring, and after that is done, Owning (item's) site can check in the item
and set the status to missing. Total process done by: |
|
11.
Invoice and Payment: |
Aug 9 |
August 15 |
Whenever each of the
pairs (Owning and Borrowing sites) finish their item and patron
work, they can agree that one will send a bill to the other. |
Those sites which have a
net amount due (items due to be reimbursed to them, minus items
lost or irreparably damaged by their patrons) send bills to the appropriate
sites. Process starts no later
than: Here's an example of a
duo worksheet from the UO, if it
is helpful to anybody. |